The object of the project is a 100 years old house that requires complete roof renovation. The steps presented next are part of a solution selected for this project. When in doubt or need for more information, please do not hesitate to contact us.
Using proper scaffolding, the roof is completely uncovered to expose the underneath structure. The mesh elements of the wood structure will be replaced.
Materials used: roof scaffolding, gloves, safety equipment
The old mesh together with insulation cover (bitumen, foil etc.) are completely removed to get access to the old insulation (if exist) or to the base of the attic.
Materials used: removal tools
The old boards are completely removed to get access to the underneath structure of the roof and expose the insulation layer and offering the chance to examine the base structure.
Material used: removal tools, protection equipment
The old insulation and any other associated layer (underneath foil) are being completely removed to give exposure to the base layer (e.g. plaster boards).
Materials used: removal tools, protection equipment
The old structure of the roof is being either replace or reinforced, to offer a solid support for roofing layers.
Material used: matching wood beams, assembly tools
At this point the insulation material is laid down. In this case it is used STEICOflex 036 wood fiber based flexible insulation for the following reasons:
Material used: STEICOflex 036, knife
Over the insulation is laid down the vapor permeable windproof membrane STEICOmulti UDB. This is a highly vapour-permeable, airtight, windproof, and waterproof. Its role is to drive away the rain and condensation formed under the roofing tiles. Once installed, will protect the roof for many months, before being covered with tiles.
Materials used: STEICOmulti UDB
The overlap of the membranes, where there is no adhesive side available, the STEICOmulti Tape 100 mm adhesive tape is applied. This has the role to keep together separate pieces of membrane and to seal against the water.
Material used: STEICOmulti Tape 100
At this step, the last layer of insulation is added. In this project it was used STEICOuniversal dry insulating plates.
Materials used: STEICOuniversal dry
The roof rehabilitation project doesn’t look only simple, but is also efficient when using the right materials. In this case, the insulation kit consists of three key elements:
Note: This solution is recommended to the contractors being committed to quality and to the owners caring for their health, their comfort, and their budget.
This was a house built in 1950. But also the houses from the 1990s are now considered “old buildings” that need refurbishing. No wonder, because in terms of energy they no longer meet current requirements. Using the right solution, old buildings can be rehabilitated, both thermally and visually. Optimal insulation of the building envelope enables an energy level that corresponds to that of a new building. The key advantages of the solution presented are:
Note: For the rest of the building see other insulation projects too.
For more information regarding materials, tools, methods, and tips, as well as regarding technical specifications, compliance, and certification, please visit www.steico.com for insulation materials, www.ids23.de for insulation accessories, and www.coolmachines.de for blown in technology and accessories.